Toledo Molding & Die: New Facility

Bowling Green, Ohio


Mosser was hired as the design/builder for this 118,000 sf pre-engineered steel building to accommodate Toledo Molding & Die’s expanding blow molding business.

With a fast-track schedule, the facility was completed in five months despite site work beginning in one of the wettest months on record for Bowling Green since 1886.

The manufacturing facility is 112,500 sf with an additional 5,500 sf devoted to the attached offices.